Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- June 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
14 July 2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
04/HY/2006
Table 3.5 Summary of submission status under FEP-04/364/2009/A
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.7 Summary of submission status under FEP-02/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.9 Summary of submission status under FEP-01/364/2009
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.11 Summary of submission status under FEP-05/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.13 Summary of submission status under FEP-06/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.15 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006
Table 5.3 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. 04/HY/2006
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4 Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Instrumentation
Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Hoarding
erection
·
Tree
transplanting
·
Installation
of coupler in CR3
·
Drainage
diversion works
·
Site
investigation and pre-drilling works
·
Excavation
in Trough B
·
Man Kwong
Street Gate 1 & 2 setup
·
Sheet
piling
·
Retaining
wall
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
·
Major
construction works were completed and Engineer’s confirmation for completion of
work is under processing in this reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
No major
construction activity was undertaken in reporting month. Only preparation works
was commenced in the reporting month.
·
Pre-drilling
works for SCL Protection Works and CWB.
·
Timber
scaffolding for subsequent site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored
H piling works for the proposed CWB.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Guide
wall construction for diaphragm wall construction
·
Pre-drilling
for diaphragm wall construction at WCR1 area.
·
Tunnel
bored pile works at WCR1 area
·
Diaphragm
wall construction at WCR1 area
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
No major
construction activity was undertaken in reporting month.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel
fabrication of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
Pre-drilling
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 -
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Hoarding
erection
·
Tree
transplanting
·
Installation
of coupler in CR3
·
Drainage
diversion works
·
Site
investigation and pre-drilling works
·
Excavation
in Trough B
·
Sheet
piling
·
Diaphragm
wall
·
Instrumentation
at
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Major
construction works were completed and Engineer’s confirmation for completion of
work is under processing.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
Pre-drilling
works and pre-bored H piling works for both SCL protection Workers as well as
CWB.
·
Preparatory
works such as ground treatment, guide wall construction and plant establishment
for the proposed D-Wall construction works within HKCEC1.
·
All
outstanding geotechnical instrumentation for construction of CWB & SCL
Protection Works.
·
Site
investigation works for designing the proposed jet grouting works.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel bored pile and diaphragm wall
construction.
·
Diaphragm wall construction.
·
Complete guide wall and pre-drilling
for diaphragm wall construction at WCR1 Area.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm wall construction at TS1
and TPCWAE
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel fabrication of temporary
platform
·
Erection of platform to enable marine
pre-drilling
·
Marine pre-drilling
·
Trial pit at Portion XI
·
Remove existing dolphin pier
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th June to 27th
July 2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction
– details the scope and structure of the report.
Section
2 Project Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory
Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4 Monitoring Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results
– summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit
– summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7 Cumulative Construction
Impact due to the Concurrent Projects –
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass
and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central – Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they June be either constructed
or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting
month, advance piling work at FEHD Whitfield Depot
under Contract no. HY/2009/17 was commenced on 5 October 2010 and pending to construct
one pile cap. In addition, Central - Wan Chai Bypass (CWB) – Central
Interchange was ciommenced
on 21 April 2011. Moreover, Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under HY2009/19 was commenced on 24 April 2011 Finally, Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel) was
commenced on 26 April 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central
- Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at |
DP1, DP2 |
Pending
for July |
HK/2009/02 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April
2011 |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel ( |
DP1 |
Pending for
July |
HY/2009/19 |
Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr. Peter
Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Sub
Agent |
Mr. Johnny
Wong |
9725
5870 |
|||
Site Agent |
Mr. Tony
Au |
9725
5874 |
|||
Chiu Hing
Construction & Transportation Co. Ltd. |
Contractor
under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo –
Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
Mr. David Wong |
9653 8635 |
|||
Construction Manager |
Mr. Wilson Lau |
5183 1270 |
|||
Construction Manager |
Mr. Alex Tsang |
9194 9383 |
|||
Environmental Officer (Compliance
Manager) |
Mr Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms Kiwi Chan |
6227 8840 |
|||
Chun Wo –
CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Eric
Lam |
3658-3048 |
|||
Deputy Site
Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Miss
Flora Ng |
3658-3064 |
|||
Chun Wo –
CRGL Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr. Rayland
Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Cheung
Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Simon
Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
M.H. Isa |
9884
0810 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr. Brian
Gillon |
2214 7700 |
2140 6799 |
Deputy
Site Agent |
Mr. Desmond
Sze |
2214 7703 |
|||
Environmental
Officer |
Mr. |
2214 7721 |
|||
Environmental
Supervisor |
Mr. Dennis
Yu |
2214 7738 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. Simon
Tang |
3557
6358 |
|||
Head of
construction |
Andrew
Kwan |
3557
6396 |
|||
Environmental
Officer |
Samuel
Tsui |
3557
6347 |
|||
Environmental
Supervisor |
Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Tim Fung |
3557
6349 |
|||
Environmental
Supervisor |
Hilda
Lau |
3557
6378 |
|||
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
·
Major construction
work was completed and Engineer’s confirmation for completion
of work is under processing.
Contract no. HY/2009/17 -
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central
- Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Instrumentation
Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Hoarding
erection
·
Tree
transplanting
·
Installation
of coupler in CR3
·
Drainage
diversion works
·
Site
investigation and pre-drilling works
·
Excavation
in Trough B
·
Man Kwong
Street Gate 1 & 2 setup
·
Sheet
piling
·
Retaining
wall
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
·
No major
construction activity was undertaken in reporting month. Only preparation works
was commenced in the reporting month.
·
Pre-drilling
works for SCL Protection Works and CWB.
·
Timber
scaffolding for subsequent site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored
H piling works for the proposed CWB.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Guide
wall construction for diaphragm wall construction
·
Pre-drilling
for diaphragm wall construction at WCR1 area.
·
Tunnel
bored pile works at WCR1 area
·
Diaphragm
wall construction at WCR1 area
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
·
Diaphragm
wall construction at TS1 and TPCWAE.
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication
of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
Pre-drilling
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
·
Major construction
work was completed and waiting Engineer’s formal confirmation for completion of work.
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Hoarding
erection
·
Tree
transplanting
·
Installation
of coupler in CR3
·
Drainage
diversion works
·
Site
investigation and pre-drilling works
·
Excavation
in Trough B
·
Sheet
piling
·
Diaphragm
wall
·
Instrumentation
at
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
Pre-drilling
works and pre-bored H piling works for both SCL protection Workers as well as
CWB.
·
Preparatory
works such as ground treatment, guide wall construction and plant establishment
for the proposed D-Wall construction works within HKCEC1.
·
All
outstanding geotechnical instrumentation for construction of CWB & SCL
Protection Works.
·
Site
investigation works for designing the proposed jet grouting works.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel bored pile and diaphragm wall
construction.
·
Diaphragm wall construction.
·
Complete guide wall and pre-drilling
for diaphragm wall construction at WCR1 Area.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm wall construction at TS1
and TPCWAE
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel fabrication of temporary
platform
·
Erection of platform to enable marine
pre-drilling
·
Marine pre-drilling
·
Trial pit at Portion XI
·
Remove existing dolphin pier
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Valid |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 - Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 June 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table
3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary of submission status under
FEP-04/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 June 2010 |
Conditions 2.7 and 2.8 |
Submission of works schedule and location plan |
11 June 2010 and 5 August 2010 |
Condition 2.9 |
Noise Management Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 November 2010 |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
PP-RS0045-11 |
16
Dec 2010 |
21
Dec 2010 to 20 Jun 2011 |
Valid |
|
GW-RS0107-11 |
8
Feb 2011 |
16
Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11
Feb 2011 |
28
Feb 2011 to 31 Aug 2011 |
Valid |
|
GW-RS0384-11 |
29
Apr 2011 |
27
May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
9
May 2011 |
11
May 2011 to 10 Nov 2011 |
Valid |
|
GW-RS0450-11 |
20
May 2010 |
9
Jun 2010 to 8
Dec 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
WPN5213-134-C3585-01 |
21
Jan 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
9 Jun 2011 |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April 2011 |
1 June 2011 to 30 Nov 2011 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0033-11 |
19 Jan 2011 |
1 Feb 2011 to 31 Jul 2011 |
Valid |
|
GW-RS0074-11 |
28 Jan 2011 |
1 Feb 2011 to 7 Jun 2011 |
Expire |
|
GW-RS0093-11 |
2 Feb 2011 |
17 Feb 2011 to 16 Jul 2011 |
Valid |
|
GW-RS0280-11 |
30 Mar 2011 |
31 Mar 2011 to 30 Sept 2011 |
Valid |
|
GW-RS0343-11 |
11 April 2011 |
25 Apr 2011 to 10 Oct 2011 |
Valid |
|
GW-RS0369-11 |
21 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RS0377-11 |
27 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RE0311-11 |
4 May 2011 |
5 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RS0401-11 |
3 May 2011 |
18 May 2011 to 17 Nov 2011 |
Valid |
|
GW-RS0414-11 |
3 May 2011 |
9 May 2011 to 8 Nov 2011 |
Valid |
|
GW-RS0423-11 |
9 May 2011 |
22 May 2011 to 21 Nov 2011 |
Valid |
|
GW-RS0430-11 |
9 May 2011 |
16 May 2011 to 15 Nov 2011 |
Valid |
|
GW-RS0453-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0458-11 |
17 May 2011 |
21 May 2011 to 20 Nov 2011 |
Valid |
|
GW-RS0461-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0473-11 |
27 May 2011 |
01 May 2011 to 30 Nov 2011 |
Valid |
|
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011 to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011 to 12 Dec 2011 |
Valid |
|
GW-RS1154-10 |
8 Dec 2010 |
8 Jan 2011 to 7 June 2011 |
Expire |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Table 3.9 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in
Table 3.10 and Table 3.11.
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0275-11 |
24 Mar
2011 |
22 Apr
2011 20:00 – 2 June
2011 06:00 |
Expired |
Table 3.11 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
01-Mar-11 |
Condition 2.10 |
Landscape Plan |
26 Jan 2011 |
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
22 Nov 2010 |
N/A |
Valid |
|
22 Nov 2010 |
N/A |
Valid |
||
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Water
Discharge Licence (Discharge at
Portion VII) |
WT00008780-2011 |
22 Mar
2011 |
22 Mar
2011 to 31 Mar 2016 |
Valid |
Water
Discharge Licence (Discharge at |
WT00008905-2011 |
11 Apr
2011 |
11 Apr
2011 to 30 Apr 2016 |
Valid |
Table 3.13 Summary of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar 2011 |
Condition
2.8 |
Location
Plan |
15 Mar 2011 |
Condition
2.23 |
Noise Management
Plan |
6 May 2010 |
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status
on licences and/or permits on environmental protection pertinent and submission under
FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.14 and Table 3.15.
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Table 3.15 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Noise Monitoring Stations
4.1.1.
The noise
monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real
Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.4.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.5.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
·
One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
·
One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction
works are extended to include works during the hours of 1900 – 0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.7.
As referred to
in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements June be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.9.
The sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency before deployment to the site and during
each site visit. Measurements June be accepted as valid only if the calibration
level from before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air
monitoring stations for the Project are listed and shown in Table
4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(western End of Podium) |
Central |
* Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
4.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute
adjustable flow range;
·
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing a minimum
exposed area of 406 cm2;
·
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
·
Equipped with a shelter to
protect the filter and sampler;
·
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
·
Equipped with a flow recorder for
continuous monitoring;
·
Provided with a peaked roof
inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated annually.
The concern parties such as IEC shall properly document the calibration data
for future reference. All the data should be converted into standard
temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of
size 8" x 10" shall be labeled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.9.
After sampling,
the filter paper loaded with dust shall be kept in a clean and tightly sealed
plastic bag. The filter paper shall then be returned to the laboratory for
reconditioning in the humidity controlled chamber followed by accurate weighing
by an electronic balance with readout down to 0.1 mg. The balance shall be
regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting
month, the concurrent contracts are as follows:
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North
Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract no.
HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai
East
5.0.3.
The environment
monitoring schedules for reporting month and coming month are presented in Appendix
5.1.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.1.
The proposed
division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.2.
No action and
limit level exceedance was recorded during day time and restricted hour period
in the reporting month. Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.1.3.
Construction
activity under contract no. 04/HY/2006 was completed, no noise monitoring for
the contract was conducted. Noise monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed
division of noise monitoring stations for Contract no. HY/2009/18 and 04/HY/2006
are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. HY/2009/18
and 04/HY/2006
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.4. No action and limit level exceedance was recorded during
day time in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5.
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is
pending and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed
division of noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
5.1.6.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.7.
Four limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 2, 8, 14 and 24 June 2011
during restricted hour. Major
noise source was contributed from
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
5.1.8.
The commencement of construction
works for Contract no. HY/2009/15 under FEP-06/364/2009/A is pending. The
proposed division of noise monitoring stations are summarized in
Table 5.4 below.
Table
5.4 Noise
Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.9.
Noise monitoring for the tunnel works
under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed
division of noise monitoring stations are summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
5.1.10.
Three
limit level exceedances were recorded at M6 - HK Baptist Church Henrietta Secondary School on 2, 8, 14 June 2011 during day time of examination period. After checking
contractor’s work schedules and investigation found that only minor works was
conducted during monitoring and traffic noises in IECL as major noise sources contributed
in the noise monitoring. It was considered the exceedances were not related to
the Project. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2.
5.2.1.
No construction
activity with valid Construction Noise Permit was conducted during night time period
(2300 to 0700) in this reporting month.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009/A
Table 5.6 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
* Real time
noise monitoring results and graphical presentation during night time period
are for information only.
5.2.3.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring results measured in
this reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4 .
5.2.4.
The proposed
division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table 5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
5.2.5.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 5.4 .
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under
FEP-03/364/2009
5.3.1.
The proposed
division of air monitoring stations are summarized in Table 5.8 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table 5.8
Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA2a |
|
5.3.2.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.3.3.
Construction
activity under contract no. 04/HY/2006 was completed, no air monitoring for the
contract was conducted. Air monitoring for the Central Interchange works under
contract no. HY/2009/18 was commenced on 21 April 2011.The proposed division of
air monitoring stations are summarized in Table 5.9 below.
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.4.
Due to lack of electricity supply at station MA1w, 24 hr and 1 hr TSP
were rescheduled to conduct on 22 June 2011 and 23 June 2011, respectively.
5.3.5.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
5.3.6.
Air quality monitoring will be commenced depending on
the commencement of work for Contract no. HK/2009/01 under FEP-02/364/2009. The proposed
division of air monitoring stations are summarized in Table 5.10 below.
Table 5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.7.
The commencement
of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.
The proposed division of air monitoring stations are summarized in Table
5.11 below.
Table 5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
5.3.8.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (
5.3.9.
Air quality monitoring will be
commenced depending on the commencement of work for Contract no. HY/2009/15
under FEP-06/364/2009/A. The
proposed division of air monitoring stations are summarized in Table 5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE
Site Office |
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.3.10.
The proposed
division of air monitoring stations are summarized in Table 5.13 below. Air
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26
April 2011.
Table 5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St
Community Liaison Centre |
CMA2a |
|
5.3.11.
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/17 –Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.4.1.
No Inert C&D
waste was recycled in the reporting month. Details of the waste flow table are
summarized in Table 5.14
Table 5.14 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street under FEP-04/364/2009/A
5.4.2.
No inert C&D
waste was disposed of in this reporting month. Details of the waste flow table
are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. 04/HY/2006
Inert
C&D materials disposed |
NIL |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract nos. HK/2009/01
- Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.4.3.
No inert and
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.16.
Table
5.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.4.
Inert C&D
and Non-inert C&D waste was disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.17.
Table
5.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert
C&D materials disposed |
11,535 |
12,896 |
TKO137 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
24 |
42 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
1,104 |
1,104 |
N/A |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.4.5.
Inert C&D
and Non-inert C&D waste was disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/18
Inert
C&D materials disposed |
1997.3 |
3946.5 |
T.K.O. 137 |
Inert
C&D materials recycled |
58.5 |
58.5 |
N/A |
Non-inert
C&D materials disposed |
3.7 |
139.0 |
SENT Landfill |
Non-inert
C&D materials recycled |
N/A |
||
Chemical
waste disposed |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.4.6.
No inert and
no-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/15
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.7.
Inert and non-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
2.11 |
2.11 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action
Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.1.2.
No noise monitoring was undertaken in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.3.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
6.1.4.
No noise monitoring was undertaken in the reporting month.
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.5.
Four limit level exceedances were recorded at M1a - Harbour Road Sports
Centre on 2, 8,
14 and 24 June 2011 during restricted hour.
Investigation found that major traffic noise was contributed in the noise
monitoring and not related
to the Project.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
6.1.6.
No noise monitoring was undertaken in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.7.
Three limit level exceedances were recorded at M6 - HK
Contract no. HY/2009/17 – Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.2.1
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.2
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.3.1.
No exceedance was recorded in the reporting month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.3.2.
No air quality monitoring was undertaken in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.3.3.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
6.3.4.
No air quality monitoring was undertaken in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.3.5.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
6.3.6.
No air quality monitoring was undertaken in the reporting month.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.3.1
No exceednace was recorded in the reporting month.
6.3.1.
There was no
non-compliance from the site audits in the reporting period. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.3.2.
No
project-related non-compliance from monitoring was recorded in the reporting
month.
6.4.1.
There was no
particular action taken since no project-related non-compliance was recorded
from the site audits and environmental monitoring in the reporting period.
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East (CWB Tunnel).
7.0.2.
From the Monthly
EM&A report (June 2011) of Central Reclamation Phase III the key works in June
2011 are as follows:
·
Type A filling in FRAW and FRAE
above +2.5mPD
·
General filling works above
+2.5mPD in IRAE
·
Surcharging in FRAW and FRAE
·
Construction of cantilever slab
at caisson
·
Construction of storm and foul
drainage and gullies in hinterlands for Road P2 and Road D9
·
Construction of GPO boundary wall
·
Construction of PLA boundary wall
and entrance
·
Construction of Promenade
enhancement works
·
Construction of buildings at PLA
berth
·
Road P2 Underpass ramp structures
·
Precasting for retaining wall
(offsite)
·
Installation of cooling mains
discharge pipes in FRAE and FRAW
·
Construction of CWB structure
·
Backfilling of CWB structure
·
Importation of fill material
·
Strengthening of
7.0.3.
According to the
construction programme of Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II was the filling at Temporary
Causeway Bay Reclamation 1 East (TCPR1E) and Temporary Public Cargo Working
Area Reclamation (TPCWA), dredging works at Temporary Causeway Bay Reclamation
1 West (TCPR1W), dredging and filling works at Wan Chai Reclamation Stage
1(WCR1), Advanced piling works at FEHD Whitfield Depot, Central Interchange, cross-harbour
water mains and marine pre-drilling in the reporting month. The major
environmental impact was water quality impact at
7.0.4.
The major environmental
impacts generated from the Central Reclamation Phase III were located along the
coastline of Central and Admiralty while advanced piling works at FEHD Whitfield
Depot were undertaken and sheet piling, pre-drilling works at Central and tunnel works at Wan Chai East in the reporting month. No significant air, noise
impact were anticipated in the reporting month. Besides, no environmental
monitoring exceedance was recorded from the Project in the reporting
month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was insignificant.
8.0.1.
During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/17, HY/2009/18, HY/2009/19 and HK/2009/02. No non-conformance was
identified during the site audits.
8.0.2.
Four site inspections
for Contract no. HY/2009/17 were carried out during this reporting period. No
observation was recorded in this reporting month.
8.0.3.
Four site inspections
for Contract no. HY/2009/18 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
|
110602_01 |
02-Jun-11 |
Sand
bags, for protecting gully, should be replaced. |
Replace
new sandbags for gully protection |
Completion
as observed on 9- June
- 2011 |
|
8.0.4.
Four site
inspections for Contract no. HY/2009/19 was carried out during this reporting
period. No observation was recorded in
this reporting month.
8.0.5.
Major
construction works were completed and Engineer’s confirmation for completion of work is under processing in this reporting month. No site inspection for Contract no. 04/HY/2006
was carried out during this reporting period.
8.0.6.
Four site inspections
for Contract no. HK/2009/02 was carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table
8.3.
Table 8.2 Summary of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110609_01 |
09-Jun-11 |
Uncovered
waste oil container without drip tray was located next to chemical waste
storage cabinet. Contractor needs to place it properly and dispose it
regularly by register collector. |
Place
was oil container properly and dispose it regularly by register collector |
Completion
as observed on 16- June -11 |
110616_01 |
16-Jun-11 |
Drip
tray shall be provided to the oil container near the site entrance. |
Provided
drip tray to the oil container |
Completion
as observed on 23- June -11 |
110623_02 |
23-Jun-11 |
Drip
tray shall be provided underneath the air compressor at ex-Pet Garden. |
Provided
drip tray to the air compressor |
Completion
as observed on 30- June-11 |
110623_03 |
23-Jun-11 |
Stockpile
of C&D material shall be covered after daily work. |
Covered
stockpile of C&D material after daily work |
Completion
as observed on 30- June-11 |
110623_04 |
23-Jun-11 |
Silt
screen and silt curtain shall be checked and maintained after adverse
weather. |
Check
and maintain silt screen and silt curtain after adverse weather. |
Completion
as observed on 30- June-11 |
9.0.1.
No complaint, notification of summons and prosecution was received in
the reporting month. The details of cumulative complaint log and updated summary of complaints are presented in Appendix
9.1.
9.0.2.
Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting
Period |
No. of
Complaints |
June 2011 |
0 |
Sep 10 to May 11 |
0 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HY/2009/17 |
·
Pile cap construction |
·
Noise barrier shall be
implemented; and ·
Watering any dust
generating activities |
HY/2009/18 |
·
Instrumentation Manholes
and Intake Culvert Survey ·
Excavation of trial pit ·
Hoarding erection ·
Tree transplanting ·
Installation of coupler
in CR3 ·
Drainage diversion works ·
Site investigation and
pre-drilling works ·
Excavation in Trough B ·
Man Kwong Street Gate 1
& 2 setup ·
Sheet piling ·
Retaining wall |
·
Idle stockpile shall be
covered well. ·
Water spraying shall be
conducted more frequently; and ·
Noise level shall be controlled
by reducing drilling rate. |
HY2009/19 |
·
Steel fabrication of
temporary platform ·
Erection of platform to
enable marine pre-drilling ·
Marine Pre-drilling |
·
Noise level shall be controlled
by reducing drilling rate. |
HK2009/02 |
·
Tunnel bored pile works. ·
Guide wall construction for diaphragm wall
construction. ·
Pre-treatment for diaphragm
wall construction. |
·
Noise level shall be controlled
by reducing pilling rate. ·
Watering any dust
generating activities |
10.0.3. Major construction works for Contract no.
04/HY/2006 were completed and Engineer’s confirmation for completion of work is under processing in this
reporting month.